To update your project breakdown, do the following steps:

1.  From your project page, click Create on Payment Claim System tile.

2. You will be redirected to the PCS Dashboard. Click Edit Project Breakdown. 

3. Edit the details of the project breakdown by going through the navigation:

4. Once the desired changes have been made, click Save button located at the bottom center of the page.

▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝

NOTES:

1. PRICE BREAKDOWN | VARIATION BREAKDOWN

1.1 From the navigation, click Price Breakdown.

1.2 The Price Breakdown and existing Variation Breakdown items are not editable once a claim has been made. If you really wish to update these details, we require you to withdraw all your existing claims.

▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝

2. CLAIMED VARIATIONS

2.1 If there are Customer Notices made under Variation to Contract Works, the items specified in the notice can be added to the breakdown by clicking Add to Breakdown button.

2.2 A prompt will be displayed if you leave the page without saving your changes. Click Cancel to close the prompt and click Save on your project breakdown page to apply changes. Otherwise, click Leave.

▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝▝

3. DEPOSIT AND RETENTION

3.1 If you have started making progress claims, then you wouldn’t be able to change your Deposit and Retention status unless you withdraw all your existing claims.

Did this answer your question?